Two decisions settle most of the specification: how far the vehicles drive, and how long they stand still. Everything else follows.

DecisionAC chargingDC fast charging
Daily distanceUnder 50 kmOver 150 km, or high daily utilisation
Vehicle dwell timeHours — parked overnight20–40 minutes — en-route
Typical power7 kW single-phase; 11–22 kW three-phase60 kW and up
Supply neededSingle-phase or three-phase domestic supplyThree-phase with capacity for 100 A+
ConnectorType 2 (EU) / J1772 (US)CCS2 (EU) / CCS1 or NACS (US)
Install costLow — wall mounted, short cable runsHigh — foundations, supply upgrade
Best first stepWallbox plus load balancing if the supply is tightA site survey before committing

Sizing a home or small site

start here

1. Start with the supply, not the vehicle

A 22 kW wallbox on a supply that cannot carry it will nuisance-trip. Check the main fuse and the spare capacity first — if it is tight, plan for load balancing rather than a service upgrade.

2. Then the dwell time

A car parked for ten hours needs very little power. A 7 kW single-phase wallbox adds roughly 30–40 km of range per hour, which covers most overnight use.

3. Add phases only if you need the speed

11 kW and 22 kW need a three-phase supply. If the building has one, it gives a useful margin; if not, the cost of bringing it in usually outweighs the benefit for a single vehicle.

4. Plan for the second vehicle now

Cable routing, mounting position and load balancing are far cheaper to plan at the first installation than to retrofit. Wireless load balancing lets you add chargers later without touching the supply.

5. Cable length is not cosmetic

Measure from the mounted position to the charge port with the car parked as it actually parks. A cable that is 1 m short makes the installation useless.

6. Decide who pays for the electricity

If the site needs to bill drivers, you need metering and a backend — that means a connected model with OCPP from the start, not a basic unit retrofitted later.

Choosing between our ranges

quick map
One car, driveway, no fixed installation Portable Mode 2 — plug into an existing socket, take it with you.
Fixed home charging, future second car Wallbox plus load balancing.
Apartment block or shared parking Wireless Load Balancing across several wallboxes on one supply.
Fleet depot or workshop DC 20–40 kW for scheduled top-ups, wallboxes for overnight dwell.
Public, retail or highway site DC 60–240 kW, power-pooling stacks, liquid-cooled above 400 kW.
Building your own charger 20 / 30 kW modules, plus connectors and cables.

Not sure which model fits?

Describe the site — number of vehicles, hours parked, supply capacity and country — and we will recommend the smallest configuration that does the job.